Gate 2 is the third gate in the 4D change project framework. Passing Gate 2
accepts completion of the Definition phase
and
allows the project into the
Discovery
phase,
approving necessary resources for this work.
|
# |
Item |
Discussion |
Comment |
|
1 |
Investigation complete |
Investigations needed to identify a feasible and appropriate solution are
complete, e.g. technical trials and benchmarking. |
|
|
2 |
Options considered |
All
reasonable options for delivery content and methods have been assessed and
the best selected using reasonable criteria. |
|
|
3 |
Deliverables specified |
All
value-creating items that will be delivered are specified in sufficient
detail to enable sound planning and testing. |
|
|
4 |
Delivery
criteria defined |
This
includes cost, quality and time criteria by which the success of the project
is assessed. |
|
|
5 |
Interdependencies aligned |
Agreement
and alignment achieved with other projects and work on which this project
depends.
Projects
which are dependent on this one are aligned with its schedule. |
|
|
6 |
Plans for
managing communication and commitment included |
This may be
separate document for larger projects or may be contained in the Brief and
Timeline for smaller projects. |
|
|
7 |
Methods for assuring quality are defined. |
This
includes verifying that what will be delivered is as agreed and that change
methods are sufficient.
In a larger project this may be
defined in a separate quality plan. |
|
|
8 |
Project
governance in place |
This
includes adequate reporting of progress, review meetings, risk/issue
management, specification change control and escalation process. |
|
|
9 |
Project timeline |
A
sufficiently detailed plot of who does what and when. Likely to be in
MSProject or a spreadsheet. |
|
|
10 |
Resources agreed |
This
includes all people, including full-time and part-time work, internal and
external people, plus other materials such as computers and rooms as
appropriate. |
|
|
11 |
Business
case complete and acceptable |
The full
business case should now be clear, including benefits and accurate costs. |
|
|
12 |
Ready for
next stage |
Project
resources are identified and allocated, including the project manager, team
member. |
|
|
13 |
Appropriate
documentation complete |
At minimum
this is an updated Brief and Timeline. Additional documents may be
appropriate depending on project size. |
|
|
14 |
Functional
manager agrees with plan |
The key
functional manager(s) involved agree with the plan of action and are ready
to provide defined collaboration, for example allocating people to needed
work. |
|
|
15 |
Executive
sponsor agrees with plan |
The
executive sponsor agrees with the plan, and is ready to provide appropriate
high-level support. |
|